Liquidated Damages Dispute Review

Engaged to provide an independent review into liquidated damages at a construction site in South East Queensland. Climate Resilience supported the contractor by critically reviewing the estimating process and independently assessing what constituted a reasonable risk price and allocation for wet weather delay. The final report detailed the meteorological evidence, concluding that the impacts arose from a 99th percentile wet weather period over the project delivery phase. It was determined that the contractor could not reasonably have foreseen such conditions at tender, nor was it practicable to plan for them. T